Assn Element (SetAssignmentWorkData)
Applies to: Office 2010 | Project 2010 | Project Server 2010 | SharePoint Server 2010
In this article
Attributes
Child Elements
Parent Elements
Occurrences
Specifies the identity of the assignment to change with a work data update and contains change information.
<Assn
ID = "Text">
</Assn>
Attributes
Attribute |
Description |
---|---|
ID |
Required Text. Specifies the globally unique identifier (GUID) of the assignment. Values must be in the form "HHHHHHHH-HHHH-HHHH-HHHH-HHHHHHHHHHHH" where "H" represents a hexadecimal digit between "'0" and "F". |
Child Elements
Parent Elements
Occurrences
Minimum: 1 Maximum: Unbounded |
Remarks
Each Assn element can contain either a single Change element, or one or more PeriodChange elements.
Example
The following example uses two Assn elements. The first Assn element contains a simple work data update defined with the Change element. The second Assn element contains a timephased work data update defined with the PeriodChange element.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Assn ID="6c9888a8-a782-47ac-a905-e84ad1fe0fb2">
<Change>
<ActualWork>480000</ActualWork>
<RemainingWork>960000</RemainingWork>
<TotalWork>1440000</TotalWork>
</Change>
</Assn>
<Assn ID="352eb69a-a915-4849-b9f0-3d26d0d6e0a8">
<PeriodChange>
<ActualWork Start="2007-04-16T08:00:00" End="2007-04-20T16:00:00">19200000</ActualWork>
<OvertimeWork Start="2007-04-17T16:00:00" End="2007-04-17T18:00:00">480000</OvertimeWork>
<RemainingWork>920000</RemainingWork>
</PeriodChange>
</Assn>
</Proj>