AccrueAt enumeration

The cost accrual mode specifies how and when resource costs are to be charged to the cost of a task.

Syntax

CSOM

enum AccrueAt 

JSOM

PS.AccrueAt

REST Interface

AccrueAt enumeration is not expliclity defined in REST. Use the values below to understand what can be returned and set.

Members

Name Value Description
NotSpecified 0 The cost accrual mode is not specified. This constant is used in place of a DBNull value.
Start 1 Costs are accrued as soon as the task assignment starts. A task assignment begins when a date is entered in the ActualStart field.
End 2 Costs are not accrued until the remaining work is zero.
Prorated 3 Costs accrue as work is scheduled to occur and as actual work is reported. This is the default value.

See Also

DraftProjectResource
EnterpriseResource
PublishedProjectResource