AccrueAt enumeration
The cost accrual mode specifies how and when resource costs are to be charged to the cost of a task.
Syntax
CSOM
enum AccrueAt
JSOM
PS.AccrueAt
REST Interface
AccrueAt enumeration is not expliclity defined in REST. Use the values below to understand what can be returned and set.
Members
Name | Value | Description |
---|---|---|
NotSpecified | 0 | The cost accrual mode is not specified. This constant is used in place of a DBNull value. |
Start | 1 | Costs are accrued as soon as the task assignment starts. A task assignment begins when a date is entered in the ActualStart field. |
End | 2 | Costs are not accrued until the remaining work is zero. |
Prorated | 3 | Costs accrue as work is scheduled to occur and as actual work is reported. This is the default value. |