Share via


ProjectDataSet.TaskRow.TASK_OVT_WORK property

Specifies the total amount of overtime work on a task.

Namespace:  WebSvcStatusing
Assembly:  ProjectServerServices (in ProjectServerServices.dll)

Syntax

'Declaration
Public Property TASK_OVT_WORK As Double
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double

value = instance.TASK_OVT_WORK

instance.TASK_OVT_WORK = value
public double TASK_OVT_WORK { get; set; }

Property value

Type: System.Double

Remarks

Read-only. When a task is created, TASK_OVT_WORK shows 0 hrs. When you enter scheduled overtime work in the sheet portion of the Task Usage view or Resource Usage view for the assignment, Project Professional rolls up the overtime work hours and calculates the total overtime work for the task.

Work is stored as thousandths of a minute. For example, 10000 indicates 10 minutes.

See also

Reference

ProjectDataSet.TaskRow class

ProjectDataSet.TaskRow members

WebSvcStatusing namespace