ProjectDataSet.ProjectRow.PROJ_OPT_MOVE_ACTUAL_TO_STATUS property
Indicates whether to move the end date of completed parts back to the status date, if the actual end data falls after the status date.
Namespace: WebSvcProject
Assembly: ProjectServerServices (in ProjectServerServices.dll)
Syntax
'Declaration
Public Property PROJ_OPT_MOVE_ACTUAL_TO_STATUS As Boolean
Get
Set
'Usage
Dim instance As ProjectDataSet.ProjectRow
Dim value As Boolean
value = instance.PROJ_OPT_MOVE_ACTUAL_TO_STATUS
instance.PROJ_OPT_MOVE_ACTUAL_TO_STATUS = value
public bool PROJ_OPT_MOVE_ACTUAL_TO_STATUS { get; set; }
Property value
Type: System.Boolean
Remarks
True if Project Server moves the end date of completed parts back to the status date; otherwise, False. PROJ_OPT_MOVE_ACTUAL_TO_STATUS maps to the Move end of completed parts after status date back to status date option on the Calculation tab of the Options dialog box in Project Professional.
The default value for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is False.
See also
Reference
ProjectDataSet.ProjectRow class