Project for the web limits and boundaries
-
Article
-
- 2 minutes to read
-
There are important limitations that you should know if you are using Project for the web. These limits apply to projects and tasks.
Project limitations
Field |
Limit |
Maximum total tasks for a project
|
1000
|
Maximum total duration for a project
|
3650 days (10 years)
|
Maximum total resources for a project
|
150
|
Maximum total links (successor only) for a project
|
600
|
Maximum total custom fields for a project
|
10
|
Task limitations
Field |
Limit |
Maximum hierarchy level
|
10 levels
|
Maximum links (successor + predecessor)
|
20
|
Maximum duration of leaf task
|
1250 days
|
Maximum duration of a summary task
|
3650 days (10 years)
|
Maximum resources assigned to a task
|
20 resources
|
Supported date range for a task
|
1/1/2000 - 12/31/2149
|