When is the Cancel option enabled within master planning in Dynamics 365 Supply Chain Management?
While executing your master plan without functionalities.
If you schedule a master plan that uses the master planning functionality to run as a batch job, the Cancel option enabled when you view the history of the plan.
Before you create a master plan.
If an item's on-hand inventory shows a total of minus 15, what will master planning do?
Treat it as zero on-hand.
Master planning assumes it's oversold and must therefore consider it when creating a planned order.
Master planning calculates the order quantity based on the item model group setting for physical inventory.
Master planning calculates the order quantity based on the item model group setting for financial inventory.
When a planned order is approved, what will master planning do?
Create an actual order at that time so that it appears on the Production order, Purchase order, or Transfer order list.
Regenerate the same order the next time master planning is run based on transactions that occur.
The planned order won't be affected the next time master planning is run.