Symptoms
When a production order is firmed, the items aren't exploded when you explode the bill of materials (BOM). However, when you manually create a work order and then estimate the production order, the items are exploded.
Resolution
The explosion that occurs when the production order is firmed will point to the planned order, but it doesn't appear that the planned order is currently firmed in this case. However, if the production order has been estimated, the explosion is triggered from the released production order where no planned order exists.