PidLidTaskActualEffort Canonical Property
Applies to: Office 2010 | Outlook 2010 | Visual Studio
Indicates the number of minutes that the user performed a task.
Associated properties: |
dispidTaskActualEffort |
Property set: |
PSETID_Task |
Long ID (LID): |
0x00008110 |
Data type: |
PT_LONG |
Area: |
Task |
Remarks
The value must be greater than or equal to 0 and less than 0x5AE980DF (1,525,252,319), where 480 minutes equal one day and 2400 minutes equal one week (eight hours in a work day and five days in a work week).
Related Resources
Protocol Specifications
[MS-OXPROPS]
Provides property set definitions and references to related Exchange Server protocol specifications.[MS-OXOTASK]
Specifies the properties and operations that are permissible for contact and personal distribution list objects.
Header Files
- Mapidefs.h
Provides data type definitions.