Partager via


WorkVariance Element

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

For a Task, WorkVariance is the difference between a task's baseline work and the currently scheduled work.

For a Resource, it is the difference between a resource's total baseline work and the currently scheduled work.

For an Assignment, it is the variance of assignment work from the baseline work, expressed as minutes x 1000.

<WorkVariance>
  FloatValue
</WorkVariance>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element