How to Migrate a DPM Server to New Hardware
Mis à jour: avril 2010
S'applique à: System Center Data Protection Manager 2010
To ensure data source protection and availability of recovery points across the process, you should create a plan for the DPM server migration process, including considerations of the following factors:
The service level agreement (SLA) that you need to maintain for the period of the migration.
The length of time that you can continue running the existing DPM server before retiring or repurposing it.
Maintenance windows for the protected computers.
To migrate a DPM server to new hardware,
Install DPM on a new server. For more information, see Installing DPM 2010 (https://go.microsoft.com/fwlink/?LinkID=179156).
Identify a protected computer to migrate and run
SetDPMServer.exe -DPMServerName <Name of new DPM server>
on the protected computer.Run the PowerShell script
Attach-ProductionServer.ps1
from the DPM Management Shell on the DPM server.Notes
For more information about using the Attach-ProductionServer script, see Installing Protection Agents Manually (https://go.microsoft.com/fwlink/?LinkID=185786).
Create protection groups on the new DPM server for the protected computers. For more information, see Configuring DPM 2010 (https://go.microsoft.com/fwlink/?LinkID=179157).
Maintain the previous DPM server until the recovery points from inactive replicas on it are no longer required.