다음을 통해 공유


Active Directory Migration Checklist

During an AD DS greenfield installation and migration, system engineers need checklists to keep up with what they should be doing to stand up a new domain.  This checklist is a working checklist, one that has been created here for peer review and peer additions.  This checklist should try and take into account all the high-level items one needs to look for and do during an AD DS migration.  This checklist is not meant to be a step-by-step guide but a high-level overview to keep track of what needs to be discovered.

For the previous Active Directory Checklist, check out the links below.

For a checklist on Active Directory Deployments check out:
https://social.technet.microsoft.com/wiki/contents/articles/40225.active-directory-domain-deployment-checklist.aspx

For a checklist on Active Directory Domain Discovery check out:
https://social.technet.microsoft.com/wiki/contents/articles/38512.active-directory-domain-discovery-checklist.aspx

  • Design new target domain
  • Start discovery (Source domain)
  • Determine the type of migration (restructure then migrate, migrate then restructure)
  • Setup and build Target domain
    • Create the network connections between the Source and Target domains
    • Create DNS forwarders from Source to Target and Target to Source domains
    • Forklift DNS zone if needed (needed if Source domain contains the zone named, the same name as the Target domain)
    • Mirror sites from the Source domain to the target domain
    • Apply schema updates
    • Apply appropriate ACLs
    • Create Target domain OU structure
  • Create trusts between Domains
  • Setup migration software in target domain (ADMT)
    • Install software
      • Target domain
    • Set Auditing
      • Source domain
      • Target domain
    • Disable SID filtering
      • Source domain
      • Target domain
    • Enable SIDHistory
      • Source domain
      • Target domain
    • Create migration user accounts
      • Source domain
      • Target domain
    • Create $$$ groups for NETBIOS names of domains
      • Source domain
      • Target domain
    • Setup and prepare password export service
      • Source domain (PDC)
  • Test migration after installation with a test user
    • Troubleshooting
  • IT training plan (ongoing)
    • Help Desk
    • Desktop team
    • Server team
    • Storage team
    • SharePoint team
    • Exchange team
    • DBA team
    • Application team(s)
    • Etc.
  • Clean up / Delete stale objects
    • Users
    • Computers
    • Groups
    • Contacts
    • Etc.
  • Prepare applications for migration
    • Pre-Migrate and synchronize service accounts from Source domain to Target domain
    • Configure applications to point to Source domain and Target domain for authentication
      • Alternate: Build virtual directory
        • Create proxy user accounts
        • Point all applications to virtual directory for authentication
    • Test authentication
    • Loop until finished
      • Troubleshooting
  • Migrate or build new GPOs
    • Loop until finished
      • Troubleshooting
  • Prepare scripts for migration of objects
    • Test group migration and synchronization
      • Loop until finished
        • Troubleshooting
    • Test user migration and synchronization
      • Loop until finished
        • Troubleshooting
    • Test computer migration
      • Loop until finished
        • Troubleshooting
  • Pre-Migrate Groups with SID History from Source domain to Target domain
  • Pre-Migrate Users with SID History from Source domain to Target domain
  • Migrate contacts from Source domain to Target domain
  • Make configuration changes to Exchange if needed
  • Create end user communication plan
    • Send EU communication email once a week for 4 weeks prior to migration
  • Prepare Computers for Migration
  • Re-Migrate all Groups
  • Re-Migrate all Users
  • User Acceptance Testing (UAT)
    • Migrate each desktop image for testing (if the business has 5 different images for desktop deployments, migrate each one)
    • Run through the "Start Live Migration" steps for the above images
    • Have real users test the migrated desktops in a live production environment
    • List all issues
    • Troubleshooting
    • Loop until comfortable, then proceed
  • START LIVE MIGRATION
    • Determine and outline back out plans for critical applications
    • Define collection of computers and users to be migrated (may or may not include servers)
      • GROUP ONE
        • Re-Migrate Groups (Collection 1)
        • Re-Migrate Users (Collection 1)
          • Users enabled in Target domain, disabled in Source domain
            • Migrate passwords (if desired)
            • Uncheck require to change password (if desired)
            • Disable firewalls
            • Migrate Computers (Collection 1)
              • Troubleshooting
        • GROUP TWO
          • Re-Migrate Groups (Collection 2)
          • Re-Migrate Users (Collection 2)
            • Users enabled in Target domain, disabled in Source domain
            • Migrate passwords (if desired)
            • Uncheck require to change password (if desired)
            • Disable firewalls
            • Migrate Computers (Collection 2)
              • Troubleshooting
        • GROUP ETC.
        • Continuously define and re-migrate users and groups
        • Move forward with migrating next round of computers and users
        • Loop until finished
          • Troubleshooting
  • File Server migration
    • Pray SIDHistory works
    • Backup current permissions
    • Lay down new permissions based on old permissions with scripts
  • Finalize migration
  • Set all users in the Source domain to have a new password that is unknown to user
    • Ensure all users in the Source domain have been disabled
    • Troubleshooting
    • Wait one business week
    • Shutdown Source domain, Domain Controllers
      • Troubleshooting
  • End engagement