PjConstraint enumeration (Project)

Contains constants that specify the type of constraint.

Name Value Description
pjALAP 1 Task occurs as late as possible in the schedule without delaying subsequent tasks.
pjASAP 0 Task occurs as soon as possible in the schedule. This is the default constraint type for tasks.
pjFNET 6 Task finishes on or after the constraint date.
pjFNLT 7 Task finishes on or before the constraint date.
pjMFO 3 Task finishes on the constraint date.
pjMSO 2 Task starts on the constraint date.
pjSNET 4 Task starts on or after the constraint date.
pjSNLT 5 Task starts on or before the constraint date.