PjProjectUpdate enumeration (Project)

Contains constants that specify the action to take with the specified tasks.

Name Value Description
pj0or100Percent 0 Sets only the Actual Start and Actual Finish dates.
pj0to100Percent 1 Sets the percent complete to reflect the update date.
pjReschedule 2 Schedules the remainder of the work to start on the update date.