Application.OptionsCalculation Method (Project)

Sets calculation options.

Syntax

expression .OptionsCalculation(Automatic, AutoTrack, SpreadPercentToStatusDate, SpreadCostsToStatusDate, AutoCalcCosts, FixedCostAccrual, CalcMultipleCriticalPaths, CriticalSlack, SetDefaults, CalcInsProjLikeSummTask, MoveCompleted, AndMoveRemaining, MoveRemaining, AndMoveCompleted, EVMethod, EVBaseline)

expression A variable that represents an Application object.

Parameters

Name

Required/Optional

Data Type

Description

Automatic

Optional

Boolean

True if the calculation mode is automatic.

AutoTrack

Optional

Boolean

True if task tracking fields automatically update resource assignments.

SpreadPercentToStatusDate

Optional

Boolean

True if edits to total task percent complete are spread to the status date.

SpreadCostsToStatusDate

Optional

Boolean

True if edits to total actual cost are spread to the status date. The SpreadCostsToStatusDate argument is ignored if AutoCalcCosts is True.

AutoCalcCosts

Optional

Boolean

True if actual costs are always calculated by Project.

FixedCostAccrual

Optional

Long

The default method used to accrue fixed costs. Can be one of the following PjAccrueAt constants: pjStart, pjEnd, or pjProrated.

CalcMultipleCriticalPaths

Optional

Boolean

True if Project calculates multiple critical paths for the project.

CriticalSlack

Optional

Integer

The maximum amount of slack allowed for critical tasks.

SetDefaults

Optional

Boolean

True if the values specified for all arguments except Automatic become the default for new projects.

CalcInsProjLikeSummTask

Optional

Boolean

True if subprojects in a master project behave like normal summary tasks. False if subprojects are calculated on their own. The default value is False.

MoveCompleted

Optional

Boolean

True if Project moves the end of completed parts after the status date back to the status date.

AndMoveRemaining

Optional

Boolean

True if Project moves the start of remaining parts back to the status date.

MoveRemaining

Optional

Boolean

True if Project moves the start of remaining parts before the status date forward to the status date.

AndMoveCompleted

Optional

Boolean

True if Project moves the end of completed parts forward to the status date.

EVMethod

Optional

Long

The default method for calculating earned value. Can be one of the following PJEarnedValueMethod constants: pjPercentComplete or pjPhysicalPercentComplete.

EVBaseline

Optional

Long

The baseline to use when calculating earned value. Can be one of the following PjBaselines constants: pjBaseline, or pjBaseline1 . . . pjBaseline10.

Return Value

Boolean

Remarks

If an argument is omitted, its default value is specified by the setting on the Schedule tab of the Project Options dialog box.

Using the OptionsCalculation method without specifying any arguments displays the Project Options dialog box with the General tab selected.