ProjectDataSet.TaskRow.TASK_PHY_PCT_COMP property
Contains the physical percent of work completed on the task.
Namespace: WebSvcProject
Assembly: ProjectServerServices (in ProjectServerServices.dll)
Syntax
'Declaration
Public Property TASK_PHY_PCT_COMP As Integer
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer
value = instance.TASK_PHY_PCT_COMP
instance.TASK_PHY_PCT_COMP = value
public int TASK_PHY_PCT_COMP { get; set; }
Property value
Type: System.Int32
Remarks
TASK_PHY_PCT_COMP is not a calculated field and must be entered. The task physical percent of work complete can be used as an alternative for calculating the budgeted cost of work performed (TASK_BCWP).