Application.UpdateTasks method (Project)
Updates the selected tasks.
Syntax
expression. UpdateTasks
( _PercentComplete_
, _ActualDuration_
, _RemainingDuration_
, _ActualStart_
, _ActualFinish_
, _Notes_
)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data type | Description |
---|---|---|---|
PercentComplete | Optional | Variant | The percent complete of the active tasks. |
ActualDuration | Optional | Variant | The actual duration of the selected tasks. |
RemainingDuration | Optional | Variant | The remaining duration of the selected tasks. |
ActualStart | Optional | Variant | The actual start date of the selected tasks. |
ActualFinish | Optional | Variant | The actual finish date of the selected tasks. |
Notes | Optional | String | Comments in the Notes field for the selected tasks. The value can be text only, not Rich Text Format (RTF) as in the Notes dialog box. |
Return value
Boolean
Remarks
Using the UpdateTasks method without specifying any arguments displays the Update Tasks dialog box.
Example
The following example creates a task named "TestTask-1", updates the task to 50% complete, and then deletes the task.
Sub Update_Tasks()
'Activate Gantt Chart
ViewApply Name:="Gantt Chart"
'Create a task
RowInsert
SetTaskField Field:="Name", Value:="TestTask-1"
SetTaskField Field:="Duration", Value:="2"
'Update the percent complete of the new task.
UpdateTasks PercentComplete:="50"
'Delete the new task
ActiveProject.Tasks("TestTask-1").Delete
End Sub