True if the resource calendar is an enterprise base calendar; False if the resource calendar is a local calendar. Read-only Boolean.

Syntax

expression. EnterpriseBaseCalendar

expression A variable that represents a Resource object.

Remarks

To enable a resource to use a local calendar, click Allow projects to use local base calendars on the Additional Server Settings page in Project Web App.

The EnterpriseBaseCalendar property is available only in Project Professional.