Material stockout list (form)
Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012
Click Production control > Inquiries > Material stockout list.
Use this form to check the status of materials that are scheduled for use in production, but that have not yet been delivered.
Navigating the form
The following tables provide descriptions for the controls in this form.
Tabs
Tab |
Description |
---|---|
View items that are scheduled for use in production but have not been delivered. |
|
Check production information, subcontractor vendor accounts and bills of materials (BOMs), and route information for the selected item. |
|
View criteria that are used to process the selected item. These include methods for calculating consumption, such as quantity and scrap, rounding up the calculations, and measuring items. |
|
Posting |
View BOM and inventory quantities included in the production, information about how the item is connected to other modules, and the planned dates for posting material consumption and back order status. |
Financial dimensions |
View dimensions, such as the department, cost center, and purpose for the selected item. |
Buttons
Button |
Description |
---|---|
Details |
View additional information about production and bill of material (BOM) lines for the selected item. |
Inventory |
View information about the selected item. The following options are available:
|
Fields
Field |
Description |
---|---|
Item number |
The unique identifier of the item that is consumed in the production. The same item number can be included in the production's BOM more than once. |
Production |
The production number of the production to which the bill of material line belongs. |
Raw material date |
The scheduled date for material consumption. |
Estimated |
The estimated quantity or volume of the item that is used in the production. The Consumption is field on the Setup tab displays whether the consumption is variable or constant. The calculation is as follows:
When calculating consumption, you also include variable or constant scrap. For more information, see the Variable scrap and Constant scrap fields. |
Started |
The quantity of items released to production in the BOM unit. For more information, see BOM unit. The BOM unit can be recalculated to the inventory unit. For more information, see Unit conversions (form). |
Released quantity |
The consumption that is released to the production in the BOM unit, but that has not yet been included in the cost accounting. |
Remaining quantity |
The consumption that must be released to production in the BOM unit with regard to the estimated quantity in the Estimated field. This occurs in the start or reporting as finished phases by using a release journal. For more information, see BOM unit. |
Position |
The position of the BOM line. It can contain an alphanumeric string of up to 10 characters. Use the position as a reference to a position number on a drawing of the item. |
Vendor account |
For lines with a vendor account, define a vendor number that purchase orders should be created for. If you leave this field blank, the vendor is obtained through the operations resource on the attached operation. For more information, see Purchase order (form). |
Line type |
BOM lines can be composed of several types. Each type has its own function. The following options are available:
|
Reservation |
Specify whether the item automatically should be reserved from on-hand inventory. The reservation in the on-hand inventories is made upon the first cost estimate of the production. The following options are available:
|
Calculation |
A selected check box indicates that the BOM line affects estimation. When the check box is selected, the line is included in estimation. Estimation calculates the expected cost price and sales price. For more information, see the Estimation form. |
Sub-BOM |
The BOM number for a related sub-BOM. If the field is blank, only the active BOMs are used. |
Subroute |
The route number for a related subroute. If the field is blank, only the active routes are used. |
Formula |
The formula that is used to calculate consumption. |
Quantity |
The quantity units of the item required to produce one finished item. If there is a gain of the current item, specify a negative quantity. In the production table (P), the dimensions for the finished item are entered as follows:
In the production's BOM (B), measurements are specified as follows: Formula = Height * Width * Constant
|
Per series |
Specify the number of units that the quantity applies to. |
Unit |
Specifies the unit in which consumption is expressed. The unit identifier is retrieved from the BOM unit field in the Released product details form. |
Consumption is |
Specifies whether the estimate concerns a variable or constant amount or quantity. Variable consumption means that the quantity of units used in the finished product is proportional to the quantity scheduled for the production order. The consumption is calculated as follows: Quantity in the production order * Quantity in the bill of material. Constant consumption is used to define a fixed amount or quantity for the production items, such as start-up costs. Consumption is calculated as follows: Consumption = Quantity in the BOM. |
Flushing principle |
Select the method of registering item consumption against a production order. The following options are available:
If you leave the field blank, the Flushing principle setting on the item is used. Note To enable automatic consumption, you use this field together with the Automatic BOM consumption field when you update the production order. |
Constant scrap |
Specify a constant scrap value. Scrap is calculated in the unit specified on the BOM line. Scrap is used to calculate adjusted raw material consumption on BOM lines. For more information, see BOM versions and lines (form). |
Variable scrap |
Specify a variable scrap value. Variable scrap is indicated as a percentage, where 10 percent is written as 10.00. Scrap is used to calculate corrected raw material usage on the BOM lines. For more information, see BOM versions and lines (form). |
Rounding-up |
Use this field to round a cost estimated quantity to the Multiples value. Use rounding if the raw materials are always used in fixed quantities. The following options are available:
|
Multiples |
The rounding multiple. You can use this field for rounding consumption, quantities, or measurements. This field can be changed until the production is reported as finished. For more information, see Rounding-up. |
Height |
The calculation factor for height that is used in the calculation of raw materials consumption, if this is proportional with the measurements defined in the production order. This field can be changed until the production order is reported as finished. After a change, you must cost-estimate the production order again to incorporate the changes. |
Width |
The calculation factor for width that is used to calculate raw materials consumption, if this is proportional with the measurements defined in the production order. This field can be changed until the production order is reported as finished. |
Depth |
The calculation factor for depth that is used in the calculation of raw materials consumption, if this is proportional with the measurements defined in the production order. This field can be changed until the production order is reported as finished. For more information, see Formula. |
Density |
The calculation factor for density that is used in the calculation of raw materials consumption, if this is proportional with the measurements defined in the production order. This field can be changed until the production order is reported as finished. For more information, see Formula. |
Constant |
The calculation factor for constant that is used in the calculation of raw materials consumption, if this is proportional with the measurements defined in the production order. This field can be changed until the production order is reported as finished. For more information, see Formula. |
Estimated |
The cost-estimated quantity or amount of the item to be included in the defined production. The value is displayed in the inventory unit. The consumption is calculated when estimation is executed. For variable consumption, the following formula is used in calculating the consumption: Quantity in the production order * Quantity in the bill of material = Consumption is. This determines whether the consumption is variable or constant. For more information, see Consumption is. When the production has the status Created, 0.00 is displayed in the Quantity field. |
Remaining quantity |
The consumption that is released to the production with regard to the estimated quantity. The value is displayed in the inventory unit. |
Reference type |
The type of relation that there is to objects in other modules. Together with the Reference number and Reference lot fields, this field contains the complete reference to the object that the production line refers to. The following options are available:
The reference to, for example, a purchase line is structured so that the reference type is Purchase, and the reference number is the purchase number of the current purchase. The reference lot is the lot number of a specific purchase line under the current purchase. If the line in the production BOM generated a purchase, you can view the reference to that purchase directly from the generated reference. If a field is blank, there are no attachments to objects in other modules. The value cannot be changed. |
Reference number |
A reference to sales, purchases, productions, or production lines. The field depends on the selection in the Reference type field. Together with the Reference type and Reference lot fields, this field contains the complete reference to the object that the production line refers to. The reference to, for example, a purchase line is structured so that the reference type is Purchase, and the reference number is the purchase number of the current purchase. The reference lot is the lot number of a specific purchase line in the current purchase. If the line in the production BOM generates a purchase, you can view the reference to that purchase directly from the reference generated. If a field is blank, there are no attachments to objects in other modules. The value cannot be changed. |
Reference lot |
The lot number that is referred to. Together with the Reference type and Reference number fields, this field contains the complete reference to the object that the production line refers to. The reference to, for example, a purchase line is structured so that the reference type is Purchase, and the reference number is the purchase number of the current purchase. The reference lot is the lot number of a specific purchase line under the current purchase. If the line in the production BOM generated a purchase, you can view the reference to that purchase directly in the generated reference. If a field is blank, there are no attachments to objects in other modules. The value cannot be changed. |
Raw material date |
The planned date for the consumption of the raw material. |
Raw material time |
The scheduled time for the consumption of the raw material. |
Remain status |
The steps that remain to be performed for a specific BOM line. The back order status is related to the production's back order status. For more information, see Production orders (form). The following options are available:
|
Constant released |
A selected check box indicates that constant consumption has been released. |
Finished picking |
A selected check box indicates that the picking list journal has been posted with the End field selected. |
Department |
Specify a department dimension. |
CostCenter |
Specify a cost center dimension. |
ExpensePurpose |
Specify a purpose dimension. |
Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).