View booking details (form)
Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2
Click Project management and accounting > Common > Projects > All projects. Open a project for which role assignments have been made. On the Project team and scheduling FastTab, select one or more lines for role assignments. Depending on the version of Microsoft Dynamics AX you are using, do one of the following:
In Microsoft Dynamics AX 2012 R3: Click View booking details.
In cumulative update 7 for Microsoft Dynamics AX 2012 R2: Click View reservation details.
Note
In cumulative update 7 for Microsoft Dynamics AX 2012 R2, this form is called Worker reservation details.
–or–
Click Project management and accounting > Common > Project resources > Resources. On the Action Pane, on the Project resource tab, in the Reserve group, click one of the following buttons, depending on the version of Microsoft Dynamics AX you are using:
In Microsoft Dynamics AX 2012 R3: Click Booking details.
In cumulative update 7 for Microsoft Dynamics AX 2012 R2: Click Reservation details.
Note
When this form is opened from the Resources list page, it is called Booking details form.
Use this form to review the details about worker reservations on a specific project. You can see whether a worker is soft-booked or hard-booked for a project, the company the worker is employed by, and the worker’s cost price.
The form provides two ways for you to view a worker’s availability. By default, the grid in the form uses colors to indicate workers’ available capacity. You can also choose to add text descriptions of availability status to the cells in the grid.
The following table indicates the meaning of each color that is used in the grid.
Color |
Status |
---|---|
Green |
Available |
Light Blue |
Partially available |
Dark Blue |
Booked |
Red |
Overbooked |
Gray |
Non-working day |
Tasks that use this form
Key tasks: Create a schedule based on a project in Microsoft Dynamics AX 2012 R2 CU7 and AX 2012 R3
Navigating the form
The following tables provide descriptions for the controls in this form.
Filters
Filter |
Description |
---|---|
Start date and End date |
Specify the date range for which you want to review worker reservation details. |
Format for date range view |
Select the unit of time for which to view details about worker reservations, such as Weeks. |
Buttons
Button |
Description |
---|---|
Confirm This control is available only if Microsoft Dynamics AX 2012 R3 is installed. |
Convert selected soft-booked hours to hard-booked hours. |
Cancel reservation Cancel booking |
Release workers from the hard booking or soft booking reservations that are represented by the selected cells in the grid. |
Fields
Field |
Description |
---|---|
Display availability descriptions This control is available only if Microsoft Dynamics AX 2012 R3 is installed. |
Select this check box to display text descriptions of worker availability in the schedule grid. |
Worker |
The name of the worker whose time has been reserved for the project. |
ID |
The identifier of the project or quotation for which booking hours are being viewed. |
Project or quotation name |
The name of the project or quotation for which booking hours are being viewed. |
Booking type |
An indication of whether the worker has been tentatively assigned (soft booked) or firmly committed (hard booked) to the project. |
Legal entity |
The entity that employs the worker. |
Cost price |
The worker’s current hourly cost rate. |
Project manager or sales responsible |
The name of the worker who is responsible for the project or quotation. |
Customer |
The customer that is associated with the project or quotation. |
See also
Key tasks: Create a schedule based on a project in Microsoft Dynamics AX 2012 R2 CU7 and AX 2012 R3
Key tasks: Assign workers to projects based on availability
Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).