Task.Baseline2DurationText property (Project)
Gets or sets a string representation of the baseline duration of a task. Read/write String.
Syntax
expression. Baseline2DurationText
expression An expression that returns a Task object.
Remarks
The Baseline2DurationText property is used for manually scheduled tasks. When you convert a manually scheduled task to an auto-scheduled task, if Baseline2DurationText has any value, you should convert the value to a date for the Baseline2Duration property.
Support and feedback
Have questions or feedback about Office VBA or this documentation? Please see Office VBA support and feedback for guidance about the ways you can receive support and provide feedback.
Feedback
https://aka.ms/ContentUserFeedback.
Kommer snart: I hele 2024 udfaser vi GitHub-problemer som feedbackmekanisme for indhold og erstatter det med et nyt feedbacksystem. Du kan få flere oplysninger under:Indsend og få vist feedback om