Task.Baseline2FinishText property (Project)
Gets or sets a string representation of the baseline finish date of a task. Read/write String.
Syntax
expression. Baseline2FinishText
expression An expression that returns a Task object.
Remarks
The Baseline2FinishText property is used for manually scheduled tasks. When you convert a manually scheduled task to an auto-scheduled task, if Baseline2FinishText has any value, you should convert the value to a date for the Baseline2Finish property.