Freigeben über


Work Element

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

For a Task, Work is the total amount of work scheduled to be performed on a task by all assigned resources.

For a Resource, it is the total amount of work scheduled to be performed by a resource on all assigned tasks.

For an Assignment, it is the total amount of work scheduled to be performed by a resource on a task.

For a Baseline, it is the scheduled work for the task, resource or assignment when the baseline was saved.

<Work>
  DurationValue
</Work>

Parent Elements

TaskResourceAssignmentBaseline

Occurrences

Minimum: 0

Maximum: 1

Example

The following example shows there are 16 hours of work scheduled for all resources on task T3. Because the scheduled duration is also 16 hours, work on the task hasn't started. The Work value PT16H0M0S specifies 16 hours, 0 minutes, 0 seconds. The PT stands for Project Time and is for internal use.

<Task>
   <UID>3</UID>
   <ID>3</ID>
   <Name>T3</Name>
   <Type>1</Type>
   <IsNull>0</IsNull>
   <CreateDate>2007-11-09T15:30:00</CreateDate>
   <WBS>3</WBS>
   <OutlineNumber>3</OutlineNumber>
   <OutlineLevel>1</OutlineLevel>
   <Priority>500</Priority>
   <Start>2007-11-15T08:00:00</Start>
   <Finish>2007-11-16T17:00:00</Finish>
   <Duration>PT16H0M0S</Duration>
   <DurationFormat>53</DurationFormat>
   <Work>PT16H0M0S</Work>
   . . .
</Task>

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element