Task Element
This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.
There must be at least one task in each Tasks collection.
<Task>
ComplexTypeValue
</Task>
Parent Elements
Child Elements
Element |
Required / Optional |
Description |
---|---|---|
Required |
Unique ID for the task. |
|
Optional |
Position identifier of the task in the list of tasks. |
|
Optional |
Name of the task. |
|
Optional |
Type of the task (fixed units, fixed duration, or fixed work). |
|
Optional |
Indicates whether a task is null. |
|
Optional |
Date and time that a task was added to a project. |
|
Optional |
Name of the individual who is responsible for a task. |
|
Optional |
A unique code (work breakdown structure) used to represent a task's position within the hierarchical structure of tasks. |
|
Optional |
Right-most level of the task. For example, if the task WBS is A.01.03, the right-most level is 03. |
|
Optional |
Number that indicates the level of a task in the project outline hierarchy. |
|
Optional |
Indicates the exact position of a task in the outline. |
|
Optional |
Indicates the level of importance assigned to a task |
|
Optional |
Date and time that a task is scheduled to begin. |
|
Optional |
The date and time that a task is scheduled to be completed. |
|
Optional |
Total span of active working time for a task. |
|
Optional |
Format used to show the duration of the task. |
|
Optional |
Total amount of work scheduled to be performed on a task by all assigned resources. |
|
Optional |
Date that represents the end of the actual portion of a task. |
|
Optional |
Date the remaining portion of a task is scheduled to resume. |
|
Optional |
Indicates whether the task can be resumed. |
|
Optional |
Indicates whether scheduling for a task is effort-driven. |
|
Optional |
Indicates whether a task is a recurring task. |
|
Optional |
Indicates whether an assigned resource on a task has more work than can be done within the normal working capacity. |
|
Optional |
Indicates whether the task's duration is flagged as an estimate. |
|
Optional |
Indicates whether a task is a milestone. |
|
Optional |
Indicates whether a task is a summary task. |
|
Optional |
Indicates whether a task has room in the schedule to slip, or if it is on the critical path. |
|
Optional |
Indicates whether the task is an inserted project. |
|
Optional |
Indicates whether the inserted project is a read-only project. |
|
Optional |
Source location of the inserted project. |
|
Optional |
Indicates whether the task is linked from another project or whether it originated in the current project. |
|
Optional |
Source of an external task. |
|
Optional |
The earliest date that a task can begin, based on the early start dates of predecessor and successor tasks and other constraints. |
|
Optional |
The earliest date that a task can finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay. |
|
Optional |
The latest date that a task can start without delaying the finish of the project. |
|
Optional |
The latest date that a task can finish without delaying the finish of the project. |
|
Optional |
The difference between a task's baseline start date and its currently scheduled start date. |
|
Optional |
The amount of time that represents the difference between a task's baseline finish date and its current finish date. |
|
Optional |
The difference between a task's baseline work and the currently scheduled work. |
|
Optional |
The amount of time that a task can be delayed without delaying any successor tasks. |
|
Optional |
The amount of time a task can be delayed without delaying a project's finish date. |
|
Optional |
A task expense that is not associated with a resource cost. |
|
Optional |
Indicates how fixed costs are to be charged, or accrued, to the cost of a task. |
|
Optional |
The current status of a task, expressed as the percentage of the task's duration that has been completed. |
|
Optional |
The current status of a task, expressed as the percentage of the task's work that has been completed. |
|
Optional |
The total scheduled, or projected, cost for a task. |
|
Optional |
Sum of the actual overtime cost for the task. |
|
Optional |
Amount of overtime scheduled to be performed by all resources assigned to a task and charged at overtime rates. |
|
Optional |
Date and time that a task actually began. |
|
Optional |
Date and time that a task actually finished. |
|
Optional |
Span of actual working time for a task so far, based on the scheduled duration and current remaining work or percent complete. |
|
Optional |
Costs incurred for work already performed by all resources on a task, along with any other recorded costs associated with the task. |
|
Optional |
Costs incurred for overtime work already performed on a task by all assigned resources. |
|
Optional |
Amount of work that has already been done by the resources assigned to a task. |
|
Optional |
Actual amount of overtime work already performed by all resources assigned to a task. |
|
Optional |
Total amount of non-overtime work scheduled to be performed by all resources assigned to a task. |
|
Optional |
Total amount of non-overtime work scheduled to be performed by all resources assigned to a task. |
|
Optional |
Amount of time required to complete the unfinished portion of a task. |
|
Optional |
Remaining scheduled expense of a task that will be incurred in completing the remaining scheduled work by all resources assigned to a task. |
|
Optional |
Remaining scheduled overtime expense for a task. |
|
Optional |
Amount of remaining overtime scheduled by all assigned resources to complete a task. |
|
Optional |
Costs incurred for work already done on a task, up to the project status date or today's date. |
|
Optional |
Difference between how much it should have cost to achieve the current level of completion on the task and how much it has actually cost. |
|
Optional |
Start or finish constraint on a scheduled task. |
|
Optional |
Refers to a valid UID for a project calendar. |
|
Optional |
Indicates the constrained start or finish date as defined in ConstraintType. |
|
Optional |
Date entered as a deadline for the task. |
|
Optional |
Indicates whether the leveling function can delay and split individual assignments (rather than the entire task) to resolve overallocations. |
|
Optional |
Indicates whether the resource leveling function can cause splits on remaining work on a task. |
|
Optional |
Amount of time that a task is to be delayed from its early start date as a result of resource leveling. |
|
Optional |
Format for expressing the duration of the delay. |
|
Optional |
Start date of a task as it was before resource leveling was done. |
|
Optional |
Finish date of a task as it was before resource leveling was done. |
|
Optional |
Title or explanatory text for a hyperlink associated with a task. |
|
Optional |
Address for a hyperlink associated with a task. |
|
Optional |
Specific location in a document within a hyperlink associated with a task. |
|
Optional |
Indicates whether the scheduling of the task takes into account the calendars of the resources assigned to the task. |
|
Optional |
Notes entered about a task. |
|
Optional |
Indicates whether the Gantt bars and Calendar bars for a task are hidden. |
|
Optional |
Indicates whether the summary task in a Gantt chart displays information rolled up from subtasks. |
|
Optional |
Cumulative timephased baseline costs up to the status date or today's date; also known as budgeted cost of work scheduled. |
|
Optional |
Cumulative value of the task's timephased percent complete multiplied by the task's timephased baseline cost, up to the status date or today's date; also known as budgeted cost of work performed. |
|
Optional |
Physical percent of the total work on a task that has been completed. |
|
Optional |
Indicates the type of earned value method to use. |
|
Optional |
Specifies the predecessor task of the current task. |
|
Optional |
Specifies the duration through which actual work is protected. |
|
Optional |
Specifies the duration through which actual overtime work is protected. |
|
Optional |
Collection of baseline values of the task. |
|
Optional |
New in Microsoft Office Project 2007. Indicates whether the task is published. |
|
Optional |
New in Project 2007. Name of the task status manager. |
|
Optional |
New in Project 2007. Start date of the deliverable. |
|
Optional |
New in Project 2007. Finish date of the deliverable. |
|
Optional |
New in Project 2007. Indicates whether the task has an associated deliverable or a dependency on an associated deliverable. |
|
Optional |
New in Project 2007. A task-level enterprise custom field value. |
|
Optional |
New in Project 2007. A project-level enterprise custom field value. |
|
Optional |
Specifies the value of a task custom field. |
|
Optional |
Specifies the value of a task outline code. |
|
Optional |
Timephased data associated with the task. |
|
Optional |
If the task is a subproject, specifies the inserted subproject data. |
Occurrences
Minimum: 0 Maximum: Unbounded |
Example
In the following example, the task UID = 4 although the task ID = 3, because a task was deleted before task T3 was created. UID values must be unique within a project. Because there is no custom WBSMask defined, the task WBS value is the same as the OutlineNumber.
<Task>
<UID>4</UID>
<ID>3</ID>
<Name>T3</Name>
<Type>1</Type>
<IsNull>0</IsNull>
<CreateDate>2007-11-13T14:33:00</CreateDate>
<WBS>1.2</WBS>
<WBSLevel>2</WBSLevel>
<OutlineNumber>1.2</OutlineNumber>
<OutlineLevel>2</OutlineLevel>
<Priority>500</Priority>
<Start>2007-11-14T08:00:00</Start>
<Finish>2007-11-15T17:00:00</Finish>
<Duration>PT16H0M0S</Duration>
<DurationFormat>53</DurationFormat>
<Work>PT0H0M0S</Work>
<ResumeValid>0</ResumeValid>
<EffortDriven>0</EffortDriven>
<Recurring>0</Recurring>
<OverAllocated>0</OverAllocated>
<Estimated>1</Estimated>
<Milestone>0</Milestone>
<Summary>1</Summary>
<Critical>1</Critical>
<IsSubproject>0</IsSubproject>
<IsSubprojectReadOnly>0</IsSubprojectReadOnly>
<ExternalTask>0</ExternalTask>
<EarlyStart>2007-11-14T08:00:00</EarlyStart>
<EarlyFinish>2007-11-15T17:00:00</EarlyFinish>
<LateStart>2007-11-14T08:00:00</LateStart>
<LateFinish>2007-11-15T17:00:00</LateFinish>
<StartVariance>0</StartVariance>
<FinishVariance>0</FinishVariance>
<WorkVariance>0</WorkVariance>
<FreeSlack>0</FreeSlack>
<TotalSlack>0</TotalSlack>
<FixedCost>0</FixedCost>
<FixedCostAccrual>3</FixedCostAccrual>
<PercentComplete>0</PercentComplete>
<PercentWorkComplete>0</PercentWorkComplete>
<Cost>0</Cost>
<OvertimeCost>0</OvertimeCost>
<OvertimeWork>PT0H0M0S</OvertimeWork>
<ActualDuration>PT0H0M0S</ActualDuration>
<ActualCost>0</ActualCost>
<ActualOvertimeCost>0</ActualOvertimeCost>
<ActualWork>PT0H0M0S</ActualWork>
<ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
<RegularWork>PT0H0M0S</RegularWork>
<RemainingDuration>PT16H0M0S</RemainingDuration>
<RemainingCost>0</RemainingCost>
<RemainingWork>PT0H0M0S</RemainingWork>
<RemainingOvertimeCost>0</RemainingOvertimeCost>
<RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
<ACWP>0</ACWP>
<CV>0</CV>
<ConstraintType>0</ConstraintType>
<CalendarUID>-1</CalendarUID>
<LevelAssignments>1</LevelAssignments>
<LevelingCanSplit>1</LevelingCanSplit>
<LevelingDelay>0</LevelingDelay>
<LevelingDelayFormat>8</LevelingDelayFormat>
<IgnoreResourceCalendar>0</IgnoreResourceCalendar>
<HideBar>0</HideBar>
<Rollup>1</Rollup>
<BCWS>0</BCWS>
<BCWP>0</BCWP>
<PhysicalPercentComplete>0</PhysicalPercentComplete>
<EarnedValueMethod>0</EarnedValueMethod>
<IsPublished>1</IsPublished>
<CommitmentType>0</CommitmentType>
</Task>