ActualCost Element
This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.
For a Task, ActualCost is the costs incurred for work already performed by all resources on a task, along with any other recorded costs associated with the task.
For a Resource, it is the sum of costs incurred for the work already performed by a resource for all assigned tasks.
For an Assignment, it is the cost incurred for work already performed by a resource on a task.
<ActualCost>
DecimalValue
</ActualCost>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
See Also
Concepts
Task Elements and XML Structure
XML Schema for the Tasks Element
Resource Elements and XML Structure
XML Schema for the Resources Element