PercentWorkComplete Element

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

For a Task, PercentWorkComplete is the current status of a task, expressed as the percentage of the task's work that has been completed.

For a Resource, it is the current status of all tasks assigned to a resource, expressed as the total percentage of the resource's work that has been completed.

For an Assignment, it is the current status of an assignment, expressed as the percentage of the assignment's work that has been completed.

<PercentWorkComplete>
  IntegerValue
</PercentWorkComplete>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element