Revenue recognition overview

Applies To: Project Operations Integrated with ERP

Note

In a recent product update, the Update labels for revenue recognition and related forms and processes in Project Operations feature renamed estimates to revenue recognition. Depending on whether the feature is enabled, terminology might reference either estimate or revenue recognition. In Dynamics 365 Project Operations, revenue recognition principles vary based on the selected billing method for a project or portion of the project. This article provides information about revenue recognition in Project Operations.

Transactions accounted using time and material billing method

  • Cost and revenue recognition are connected. Use the Project Operations Integration journal to post transaction cost and unbilled sales.

  • The project cost and revenue profile determines if unbilled sales transactions go to the general ledger. If you select Accrue revenue, the system uses the WIP sales value and the Accrued revenue sales value accounts during posting. The following example shows this method.

    Transaction type Debit/Credit Amount
    WIP Sales value Debit 100
    Accrued revenue sales value Credit 100
  • Revenue is recognized during invoicing. The system uses the Invoiced revenue account during posting. The following example shows this method.

    Transaction type Debit/Credit Amount
    Customer balance Debit 120
    Sales tax payable Credit 20
    Invoiced Revenue Credit 100
  • If you accrued revenue when you posted the unbilled sales, the system reverses the accrued revenue at invoicing.

    Transaction type Debit/Credit Amount
    WIP Sales value Credit 100
    Accrued revenue sales value Debit 100

Transactions accounted by using the fixed price billing method

  • Cost and revenue recognition are separate. The Project Operations Integration journal posts the transaction cost. The process doesn't create unbilled sales transactions.
  • You can recognize revenue during invoicing if the project cost and revenue profile have Principle used for project completion calculations set to No WIP. Only use this method for short term, simple projects.
  • You can recognize revenue by using fixed price revenue estimates, with either the Completed contract or Percent completion revenue recognition method.