I have been challenged to learn how to best show the impact of delays on our construction projects.  I'm thinking of entering each delay as a separate activity and splitting the tasks affected by the delay but I would appreciate others input on how they handle this issue...

Thanks in advance..

Microsoft 365 and Office
Microsoft 365 and Office

A comprehensive suite of productivity tools and cloud services that enhance collaboration, communication, and efficiency. Combining classic Office apps with advanced Microsoft 365 features, it supports both personal and business needs

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

Answer accepted by question author

Anonymous
2014-05-25T15:47:14+00:00

If you are waiting on work from others, ensure you have built the key decision points into your schedule - I'd use a milestone and link the tasks dependent upon those decisions.  Baseline the project plan and get the owner to agree to the schedule.  Also review the key decision points and show him/her that delays in those key tasks will delay the tasks following.  If you need to delay the milestones - add a note to the task, enter the actual finish and watch the rest of the schedule shift.

You can then view the schedule variance by looking at the variance schedule.  If you were on time but the owner caused the delay, it will show zero variance for the tasks leading to the milestone and positive variance for the milestone and tasks after.

Was this answer helpful?

0 comments No comments

1 additional answer

Sort by: Most helpful
  1. Anonymous
    2014-05-25T03:50:13+00:00

    To clarify, this refers to delays caused by OTHERS outside of my project team, i.e. owner delays, etc...

    Was this answer helpful?

    0 comments No comments