Task list not syncing correctly with MS Projects

Anonymous
2016-02-25T18:49:27+00:00

So I've created a project in MS Projects and synced this project to the task list of an existing SharePoint site. When I go to the SharePoint site, the task list shows all the tasks starting and finishing at the correct time.

However, when I then go to update the project a problem occurs.

To update the project, I navigate to the task list in the SharePoint site, go to the list tab and click on "Open with Project".  When I do this, the project opens fine in MS Projects, but some of the predecessors and successors have been deleted. I then have to go in and redo all the predecessors and successors and save the file again.

Solutions I've tried:

  1. Open directly through MS Projects and then re-sync to site - no change.
  2. Delete the task list and add a new task list, and then re-sync the project - no change.
  3. Create an entirely new MS Project file and then sync to a new task list - no change.

Previously I haven't had any problems. Has anyone experienced similar problems before and found a solution?

Microsoft 365 and Office
Microsoft 365 and Office

A comprehensive suite of productivity tools and cloud services that enhance collaboration, communication, and efficiency. Combining classic Office apps with advanced Microsoft 365 features, it supports both personal and business needs

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

6 answers

Sort by: Most helpful
  1. Anonymous
    2016-03-03T05:52:59+00:00

    Hi Darren,

    Does the issue persist? Any update will be appreciated.

    Regards,

    Fraser

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments
  2. Anonymous
    2016-02-29T00:56:28+00:00

    Hi Rene,

    No the predecessors are not available in the task list, even though I update and save them in the MS Project file,

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2016-02-28T23:04:31+00:00

    I've created a fresh/new site and haven't had problems, it just seems to be this one site.

    Was this answer helpful?

    0 comments No comments
  4. Anonymous
    2016-02-27T05:28:08+00:00

    Hi DarrenGreen7293,

    Please feel free to share any updates.

    And, to further narrow down the situation, I would like to add that, whether the Predecessors is available when you,

    a. see the property is missing from the "Open with Project",

    b. go to the Task list > select the affected task item > on the TASKS ribbon, View Item > click SHOW MORE to check the Predecessors.

    Best Regards,

    Rene

    Was this answer helpful?

    0 comments No comments
  5. Anonymous
    2016-02-25T23:24:15+00:00

    Can you please try creating a fresh site and try synching project server task list to the new site ?

    Just check if that works.

    Was this answer helpful?

    0 comments No comments