Applies To: Project Operations Integrated with ERP
The Post costs feature in Dynamics 365 Project Operations lets project accountants manually move project costs between balance sheet (work in progress, or WIP) accounts and profit and loss (P&L) accounts. This feature helps ensure costs are recognized in the same period as the related revenue. Post costs moves only cost transactions; revenue is posted separately at invoicing.
Typical project accounting flows
Most organizations use one of the following approaches to manage how project costs move between balance sheet and the profit and loss statement (P&L):
P&L only – Projects are configured to post directly to P&L. Costs are recognized immediately, and no balance sheet posting occurs.
Balance sheet, with manual P&L posting – Projects are configured to post costs to the balance sheet. Project accountants use Post costs to manually move costs to P&L when recognition is appropriate.
Balance sheet, with invoice-driven P&L posting – Projects are configured to post costs to the balance sheet. When the customer is invoiced, costs automatically move from the balance sheet to P&L and revenue is recognized.
Note
Balance sheet costs don't automatically move from the balance sheet when invoiced. Post costs can manually move these balances.
Balance sheet holding – Sometimes, costs that are currently on P&L need to move back to the balance sheet. For example, when exploratory work changes into a research and development project.
The accounting flow is determined by a combination of the Cost and revenue profile, Cost and revenue profile rule, and line property capitalization setting.
Supported project types
Post costs applies only to the following project types or contract lines:
- Projects with time and material (T&M) contract lines
- Internal projects
Post costs doesn't apply to fixed price projects or investment projects. For those types, the revenue recognition process moves costs as needed.
Feature details
The following changes are included in the Post costs feature for Project Operations Integrated with ERP deployments.
- Enable using the Feature management entry
- Work with integrated project transactions with split cost and revenue records
- Support transaction posting to the balance sheet for internal projects
Enable using the Feature management entry
A new entry in the Feature management workspace turns on the Post costs menu item for integrated deployments. The menu item wasn't previously available for this deployment type.
To enable the Post costs feature, follow these steps:
- Go to System administration > Workspaces > Feature management.
- Search for Enable posting costs from the balance sheet to the income statement.
- Select the feature, and then select Enable now.
Work with integrated project transactions with split cost and revenue records
In integrated deployments, you track cost and revenue as separate transaction records. The Post costs process includes logic to check the corresponding revenue record before it allows a cost to move from profit and loss (P&L) to the balance sheet. If revenue is already accrued or the transaction is invoiced, the cost isn't eligible to move. You don't see these records in the selection window for Post costs.
Support transaction posting to the balance sheet for internal projects
As part of this feature, internal projects now support transactions posting directly to the balance sheet when you configure the Cost and revenue profile. Previously, there was no way to move costs out of the balance sheet, but now Post costs enables this flow.