Resource requirements are defined by the Project manager to establish the resources needed to execute the work on the project. Complete the following steps to define a resource requirement.
- In the Work breakdown structure, create one or more tasks.
- Assign a generic team member to each task. The assignments will update the total effort of the project team member.
- On the Team Member tab, select the team member and then select Generate Requirement.
For information about how to modify the resource requirement, see Update Resource requirement details to modify the resource requirement.