You can calculate capacity load on scheduled work orders to get an overview of the work load on resources for a specific period. Calculations can be made for the following resources: Maintenance workers, worker groups, tools, and assets.
Click Asset management > Inquiries > Schedule > Capacity load.
In the Calculate capacity load dialog > Show field, select which load type you want to calculate: Capacity, Reserved, or Remainder.
Select Yes on the Skip zero toggle button if you do not want to show results containing zero.
Select the resource types for which you want to calculate capacity load by selecting Yes on the relevant toggle buttons: Worker, Maintenance worker group, Tool, and Asset.
Select the start date for the calculation in the From date field.
In the Interval type field, select the interval for the calculation: Day, Week, Month, or Quarter.
In the Period frequency field, insert the number of intervals you want to calculate. For example, if you have selected Day as the interval type, and you enter the number "5" in this field, a calculation of five days from the start date will be made.
Click OK to start the calculation.
The figure below shows the result of a calculation covering three weeks for the load type Reserved.
[!NOTE] If you select the load types Capacity or Remainder for your calculation, the same result will be displayed if no reservations have been made for the resources in the selected period.
For information about how to calculate capacity load on maintenance schedule lines and not scheduled work orders, refer to Calculate capacity load.