Project adjustments

Applies To: Project Operations for manufacturing-based scenarios

Adjustments overview

You can configure Microsoft Dynamics 365 Project Operations so that users can make changes to posted transactions. You can adjust project transactions individually, or you can select multiple transactions at a time in a list of all project transactions. Project adjustments are used, for example, to mass-update the billable status, recalculate cost after a configuration change, or update funding sources.

Users can access the project adjustment functionality in several ways:

  • Using the Adjust transactions page that can be accessed from Project Management and accounting > Setup.
  • Using the Adjustment button on the Posted project transactions page that can be accessed from Project Management and accounting > Transactions.
  • Using the Adjustment button on the Posted project transactions page in the context of a project. This page can be accessed from Project Management and accounting > All projects.

To allow for adjustments, you must enable one or more transaction statuses from Project Management and accounting > Project Management and accounting parameters on the General tab under the section Allow adjustment of transaction status. Examples of transaction statuses include posted transactions, invoiced transactions, or eliminated transactions. Any transaction status that is set to No has transactions in that status that doesn't appear within the adjustment process as selectable for adjustment.

Adjustments process flow

The following steps show the typical flow for processing adjustments.

  1. Open the Project adjustments page.
  2. Select Select to search for transactions that meet the expected criteria for adjustment.
  3. In the list of transactions, select all transactions or a subset of the transactions for adjustment.
  4. Select Adjust, and modify the attributes on the line. Alternatively, if the values were manually specified during transaction entry, you can select to enter default system values.
  5. The list of transactions is returned, and a check mark appears in the Pending adjustment column to indicate where changes were made. Any adjustments that have pending changes are shown in the lower half of the page. There, you can make more detailed changes beyond what was shown on the previous page.
  6. Select Post to post the adjustment transactions.

Depending on the configuration, new transactions are typically created for the adjustment.

  • The Invoice Status field of the original transaction is set to Adjusted.
  • A reversal transaction is created to reverse the original transaction, and the Status field is set to Adjusted.
  • A new transaction is created that has the changes that were made during the adjustment process.

Select multiple posted project transactions at a time for adjustments and credit notes

A new feature that was introduced in the 10.0.30 release enables the selection of multiple transactions for adjustment at a time from the Posted project transactions page.

Before you can use this feature, it must be enabled in your system. Admins can use the Feature management workspace to check the status of the feature and enable it if necessary. In the Feature management workspace, search for and select Multi-select posted project transactions for adjustments and credit notes, and then select Enable now.

This feature enables the following key functionality:

  • It can be accessed from the posted transaction page within a project by using the existing Adjustment button.
  • It enables a multi-row select control on the Posted project transactions page. You can apply filters to the list page and select your records before you begin adjustments.
  • It disables the Adjustment button if any single transaction can't be adjusted, or if you select a combination of credit notes and journals together instead of individually.
  • Because of the addition of the multi-row select control, the Committed cost link in the ribbon is no longer disabled if multiple rows are selected.
  • It adds the following warning message: "You selected more than (selected number) records for adjustment. Proceeding with this action might take some time. Are you sure you would like to proceed with this action?"

This feature also removes step 2 from the process flow that was described earlier in this article. Therefore, any transactions that were selected before the Adjust transactions page was opened are included in the list of transactions for adjustment. You don't have to use the Select button to search for them.

Note

Even if this feature is disabled, you can still select multiple records for adjustment. However, only one record remains selected, and the Select transactions dialog box appears immediately after you select to open adjustments.

Adjust dates

When performing an adjustment, you're prompted for an adjustment date. This date represents the ledger date or voucher date that can impact the financial date of the transaction. The adjustment date defaults to the current date. In some cases, you need to adjust the date when the transaction took place, which is often represented as the project date. When you adjust a transaction, the system assumes that you're only adjusting the ledger date and that no edits to the project date are necessary.

A new feature introduced in the 10.0.42 release enables the ability to edit the project date or default from the adjustment date. This feature is especially useful with timesheets when you log time for the wrong day and don’t catch the error before approval and posting.

In the Feature management workspace, the Enable editing of project date for project adjustments feature can be enabled to allow for edits to project date.

When the Adjust transactions form opens, a new default values toggle is available to Set project date from adjustment date. When this option is selected, the project date defaults from the adjustment date provided.

In the Adjustments form, the bottom grid where edits can be made also now lets you make manual changes to the Project date where previously it was ready only.

Troubleshooting when transactions are missing from Adjust transactions

You may encounter an issue where you want to adjust a transaction but it doesn't appear within Adjust transactions. If an adjustment is started but interrupted by closing the browser window or from your session timing out, then the transaction may be locked in the adjustment cache. You can clear the cache and make the transaction available again by running the periodic process. Use the Clear adjustments posting cache page that can be accessed from Project Management and accounting > Periodic > Transactions to resolve this issue.

Scenarios where transactions are unavailable for adjustment

Scenario Overview Configuration Details Description
Stocked product with multiple funding sources When a sales order includes a stocked product, has multiple funding sources on the project contract, and the Enable packing slip cancellation for item requirements cancellation feature is enabled. Item requirements can't be split into multiple sales records.

Adjustment transaction statuses that can be enabled or disabled for adjustments

The following statuses can be enabled or disabled on the General tab of the Project management and accounting parameters page:

  • Posted
  • Invoice Proposal
  • Invoiced
  • Estimated
  • Eliminated
  • Beginning balance (hour)

Adjustment parameters

These parameters are listed on the Project management and accounting parameters page on the General tab under the Adjustment group and modify behavior for how adjustments are processed.

Parameter name Description
Autoupdate field If this parameter is enabled, the system recalculates cost price and sales price.
Allow closed activities Usually, transactions can't be created for closed activities. If this parameter is enabled, that behavior is overridden. Therefore, adjustments can be created for closed activities.