<Cost> Element
For a <Task>, <Cost> is the total scheduled (or projected) cost for a task, based on costs already incurred for work performed by all resources assigned to the task, in addition to the costs planned for the remaining work for the assignment.
For a <Resource>, it is the total scheduled cost for a resource for all assigned tasks, based on costs already incurred for work performed by the resource on all assigned tasks in addition to the costs planned for all remaining work.
For an <Assignment>, it is the total projected cost of the assignment when the baseline was saved.
For a <Baseline>, it is the total scheduled (or projected) cost for an assignment based on costs already incurred for work performed by the resource on a task, in addition to the costs planned for the remaining work for the assignment.
Element Properties
Property | Value |
---|---|
Data Type | Decimal |
Minimum Occurrences | 0 |
Maximum Occurrences | 1 |
Default Value | N/A |
Abstract | False |
Nillable | False |
Element Constraints | N/A |
Parent Elements
Task
Resource
Assignment
Baseline
See Also
XML Schema for the <Task> Element
XML Structure for the <Task> Element
XML Schema for the <Resource> Element
XML Structure for the <Resource> Element
XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element