<Assignment> Element
There must be at least one assignment in each <Assignments> collection.
Element Properties
Property | Value |
---|---|
Data Type | ComplexType |
Minimum Occurrences | 0 |
Maximum Occurrences | Unbounded |
Default Value | N/A |
Abstract | False |
Nillable | False |
Element Constraints | Sequence |
Parent Elements
Child Elements
List of Child Elements
Element | Required/Optional | Description |
---|---|---|
<UID> | Required | The unique ID for the assignment. |
<TaskUID> | Optional | The unique ID for the task. |
<ResourceUID> | Optional | The unique ID for the resource. |
<PercentWorkComplete> | Optional | The current status of an assignment, expressed as the percentage of the assignment's work that has been completed. |
<ActualCost> | Optional | The cost incurred for work already performed by a resource on a task. |
<ActualFinish> | Optional | The date and time when an assignment was actually completed. |
<ActualOvertimeCost> | Optional | The cost incurred for overtime work already performed by a resource on a task. |
<ActualOvertimeWork> | Optional | The actual amount of overtime work already performed by a resource on an assigned task. |
<ActualStart> | Optional | The date and time that an assignment actually began. |
<ActualWork> | Optional | The amount of work that has already been done by a resource on a task. |
<ACWP> | Optional | The costs incurred for work already performed by a resource on a task up to the project status date or today's date; also called actual cost of work performed. |
<Confirmed> | Optional | Indicates whether a resource assigned to a task has accepted or rejected the task assignment. |
<Cost> | Optional | The total scheduled (or projected) cost for an assignment. |
<CostRateTable> | Optional | Indicates which cost rate table to use for a resource on an assignment. |
<CostVariance> | Optional | The difference between the baseline cost and total cost for an assignment. |
<CV> | Optional | The difference between how much it should have cost to achieve the current level of completion on the assignment and how much it has actually cost. |
<Delay> | Optional | The amount of time a resource is to wait after the task start date before starting work on an assignment. |
<Finish> | Optional | The date and time that an assigned resource is scheduled to complete work on a task. |
<FinishVariance> | Optional | The difference between an assignment's baseline finish date and its scheduled finish date. |
<Hyperlink> | Optional | The title or explanatory text for a hyperlink associated with an assignment. |
<HyperlinkAddress> | Optional | The address for a hyperlink associated with an assignment. |
<HyperlinkSubAddress> | Optional | The specific location in a document within a hyperlink associated with an assignment. |
<WorkVariance> | Optional | The difference between an assignment's baseline work and the currently scheduled work. |
<HasFixedRateUnits> | Optional | Indicates whether an assignment has fixed rate units. |
<FixedMaterial> | Optional | Indicates whether the consumption of the assigned material resource occurs in a single, fixed amount. |
<LevelingDelay> | Optional | The amount of time that an assignment is to be delayed from the scheduled start date as a result of resource leveling. |
<LevelingDelayFormat> | Optional | The format for expressing the duration of the delay. |
<LinkedFields> | Optional | Indicates whether there are OLE links to the assignment. |
<Milestone> | Optional | Indicates whether the assignment task is a milestone. |
<Notes> | Optional | Notes about an assignment. |
<Overallocated> | Optional | Indicates whether a resource is assigned to more work on a specific task than can be done within the resource's normal working capacity. |
<OvertimeCost> | Optional | The total overtime cost for a resource assignment. |
<OvertimeWork> | Optional | The amount of overtime to be performed by a resource on a task; charged at the resource's overtime rate. |
<RegularWork> | Optional | The total amount of non-overtime work scheduled to be performed by a resource assigned to a task. |
<RemainingCost> | Optional | The costs associated with completing all remaining scheduled work by any resources on a specific task. |
<RemainingOvertimeCost> | Optional | The remaining scheduled overtime expense for an assignment. |
<RemainingOvertimeWork> | Optional | The amount of overtime work that remains on an assignment. |
<RemainingWork> | Optional | The amount of time required by a resource assigned to a task to complete an assignment. |
<ResponsePending> | Optional | Indicates whether an answer has been received from a message sent to a resource assigned to a task notifying the resource of the assignment. |
<Start> | Optional | The date and time that an assigned resource is scheduled to begin working on a task. |
<Stop> | Optional | The date the assignment was stopped. |
<Resume> | Optional | The date the assignment was resumed. |
<StartVariance> | Optional | The difference between an assignment's baseline start date and its currently scheduled start date. |
<Units> | Optional | The number of units for which a resource is assigned to a task, expressed as a percentage. |
<UpdateNeeded> | Optional | Indicates whether a TeamUpdate message should be sent to the resource assigned to a task because of changes to the start date, finish date, or resource reassignments. |
<VAC> | Optional | The variance at completion (VAC) between the baseline cost and the total cost for an assignment on a task. |
<Work> | Optional | The total amount of work scheduled to be performed by a resource on a task. |
<WorkContour> | Optional | Indicates how work for an assignment is to be distributed across the duration of the assignment. |
<BCWS> | Optional | The budgeted cost of work scheduled on the assignment. |
<BCWP> | Optional | The budgeted cost of the work performed on the assignment to-date. |
<BookingType> | Optional | Specifies the booking type of the assignment (committed or proposed). |
<ActualWorkProtected> | Optional | Specifies the duration through which actual work is protected. |
<ActualOvertimeWorkProtected> | Optional | Specifies the duration through which actual overtime work is protected. |
<CreationDate> | Optional | The date that the assignment was created. |
<ExtendedAttribute> | Optional | The value of an extended attribute (custom field). |
<Baseline> | Optional | The collection of baseline values associated with the assignment. |
<TimephasedData> | Optional | The time phased data associated with the assignment. |
See Also
XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element