<Overallocated> Element
For a <Task>, <Overallocated> indicates whether an assigned resource on a task has been assigned to more work on the task than can be done within the normal working capacity.
For an <Assignment>, it indicates whether a resource is assigned to more work on a specific task than can be done within the resource's normal working capacity.
Element Properties
Property | Value |
---|---|
Data Type | Boolean |
Minimum Occurrences | 0 |
Maximum Occurrences | 1 |
Default Value | N/A |
Abstract | False |
Nillable | False |
Element Constraints | N/A |