次の方法で共有


<RegularWork> Element

For a <Task>, <RegularWork> is the total amount of non-overtime work scheduled to be performed by all resources assigned to a task.

For a <Resource>, it is the total amount of non-overtime work scheduled to be performed for all assignments assigned to a resource.

For an <Assignment>, it is the total amount of non-overtime work scheduled to be performed by a resource assigned to a task.

Element Properties

Property Value
Data Type Duration
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task
Resource
Assignment

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element

XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element