Upgrade from AX 2012 - Post-upgrade tasks
Important
Upgrade is currently only supported from either Dynamics AX 2012 R2 or Dynamics AX 2012 R3. For each release, please update to the latest available cumulative update before upgrading to latest finance and operations application release.
This article describes the tasks that you might have to perform in finance and operations apps, like Dynamics 365 Finance and Dynamics 365 Supply Chain Management, after you complete a code and data upgrade from Microsoft Dynamics AX 2012. A process data package (PDP) that is available in Microsoft Dynamics Lifecycle Services (LCS) includes links to the following menu items. This PDP will fill in the Data validation checklist workspace. The Data validation checklist workspace lets users track a project and monitor the tasks that are required in order to complete it.
Document management
If you use document management, existing documents or attachments that are stored in the database should be migrated to Microsoft Azure Blob storage. To complete this migration, use the Migrate files button on the Migrate files tab on the Document management parameters page. This operation is not critical as document management can still access file stored in the database, but the files can take considerable database storage and the retrieval is less efficient. The file migration process will migrate all possible database files to Microsoft Azure Blob storage, reporting on any failures and continuing. If any errors are reported, attempt running the file migration process again.
If the file migration process isn’t able to complete without failure, this may be that the files stored in the database are corrupt, which Microsoft is unable to repair. If this is the case, you can request a non-business critical support case be opened to enable conversion of the attachments into note records, which will retain any previous notes as well as the names of the files that were stored in the database. Note that the files themselves cannot be recovered.
Print management
If you use Print management, the references to network printers from AX 2012 won’t be valid. You must set up and reference network printers on the Document routing page. For more information, see Install the Document Routing Agent to enable network printing.
Commerce
After you complete the upgrade from AX 2012, you must configure registers and devices.
To configure a register, click Retail and Commerce > Channels > Stores. Select the row for the channel, and then expand the Registers FactBox. Click More, click New, and complete the setup of the register.
To configure a device, click Retail and Commerce > Channel setup > POS Setup, and then click New.
Additionally, you must run all jobs (9999) for the channel database. Click Retail and Commerce > Headquarters setup > Commerce scheduler > Channel database. Select the row for the appropriate channel database, and then click Full data sync. Select the 9999 (All jobs) distribution schedule, and then click OK. Click OK again to run the job.
Service industries
After you complete the upgrade from AX 2012, you must set up resource capacity roll-up and project ledger intercompany posting.
To run the Resource capacity roll-up batch job, click Project management and accounting > Inquiries and reports > Capacity synchronization. You must run this batch job to set up the resource and resource calendar reservation data. This data will be required if you use project resource scheduling. For more information, see Project resourcing.
To enable project ledger intercompany posting, click Project management and accounting > Setup > Posting > Ledger posting setup. On the Cost accounts tab, in the Ledger account types field, select Intercompany cost, and then enter the details of the lending legal entity. On the Revenue accounts tab, in the Ledger account types field, select Intercompany revenue, and then enter details of the borrowing legal entity.
Budget planning
After you complete the upgrade from AX 2012, you must set up Budget planning columns and layouts. To complete this setup, click Budgeting > Setup > Budget planning > Budget planning configuration.
Additionally, you must update Budget planning processes so that they use the appropriate layout for each budget stage. To update Budget planning processes, click Budgeting > Setup > Budget planning > Budget planning process.
For more information about Budget planning upgrade, see Upgrade budget planning.