Contract (Total Cost) Field, Job Task Table
Displays, in local currency, the total contracted cost for the job task during the time period in the Planning Date Filter field.
The program automatically calculates and updates the contents of the field using the entries in the Total Cost (LCY) field in the Job Planning Line table. Only planning lines, with the Line Type, Contract, or Both Schedule and Contract, are included in the Contract (Total Cost) on the job task.
To see the Job Planning Lines that make up the total, choose the field.
To edit the job planning lines for the job task, click Actions, point to Functions, and then click Job Planning Lines.
Tip
For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.
Parent Tables
Table | Location |
---|---|
Job Task Table | Jobs |
Job Task Table | Jobs |