Compartilhar via


Unit Cost Field, Resource Table

Specifies the current cost of one unit of the resource.

The value is calculated based on what you entered in the Direct Unit Cost and Indirect Cost % fields, as follows.

Unit Cost= Direct Unit Cost * (1 + (Indirect Cost% / 100))

The value in the Unit Cost field may also be updated as a result of the Implement Standard Cost Change batch job, which you use after you have calculated new resource costs as a result of cost changes in Assembly BOMs.

You can change this amount, but be aware that if you do change it, the direct unit cost and indirect cost percentage are not adjusted.

For an employee with an annual salary of LCY 104,000, the direct unit cost per hour is LCY 50.00. The employee's benefits equal 30% of the salary. The following table shows that the unit cost is LCY 65.00.

Cost Type Cost

Direct Unit Cost

LCY 50.00

Indirect Cost %

30%, which = LCY 15.00

Unit Cost

LCY 65.00

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Resource Table Resources
Resource Table Resources

See Also

Reference

Resource Card

Other Resources

About Calculating Standard Cost
Implement Standard Cost Change
Assembly BOM