Efficiency Field, Prod. Order Capacity Need Table

Specifies the efficiency of the production order capacity need.

It is possible for a work center or machine center to utilize 100 hours a week but not produce 100 standard hours of work. The workers might be working at a faster or slower pace than the standard working pace, causing the efficiency of the work center to be more or less than 100 %. You can calculate as follows: efficiency = (standard hours of work produced / hours actually worked) * 100 %.