Editar

Partilhar via


Set up work centers and machine centers

Business Central distinguishes between three types of capacities that are arranged in a hierarchy where each level contains subordinate levels.

The top level is the work center group. Work centers are assigned to work center groups. Every work center can only belong to one work center group.

You can assign various machine centers to work centers. A machine center can only belong to one work center.

The planned capacity of a work center consists of the availability of the corresponding machine centers and the planned availability of the work center. The planned availability of the work center group is, therefore, the sum of all corresponding availabilities of the machine centers and work centers. Availability is stored in calendar entries.

Important

Before you set up work or machine centers, you must set up shop calendars. For more information, see Create Shop Calendars.

To set up a work center

The following steps describe how to set up a work center. The steps to set up a machine center calendar are similar, except for the Routing Setup FastTab.

  1. Choose the Lightbulb that opens the Tell Me feature. icon, enter Work Centers, and then choose the related link.

  2. Choose the New action.

  3. Fill in the fields as necessary. Hover over a field to read a short description.

  4. In the Work Center Group Code field, select the higher-level resource grouping that the work center is organized under, if relevant. Choose the New action in the drop-down list.

  5. In the Alternate Work Center field, select the work center to use if this work center isn't available or when demand exceeds its capacity. The alternate work center is for information only, and isn't automatically included in planning processes.

  6. Select the Blocked field if you want to prevent the work center from being used in any processing. This means that output can't be posted for an item that is produced at the work center. For more information, see Post Production Output.

  7. In the Direct Unit Cost field, enter the cost of producing one unit of measure at this work center, excluding any other cost elements. This cost is often referred to as the direct labor rate.

  8. In the Indirect Cost % field, enter the general operation costs of using the work center as a percentage of the direct unit cost. This percentage amount is added to the direct cost in the calculation of the unit cost.

  9. In the Overhead Rate field, enter any nonoperational costs, for example maintenance expenses, of the work center as an absolute amount.

    The Unit Cost field contains the calculated unit cost of producing one unit of measure at this work center, including all cost elements, as follows:

    Unit Cost = Direct Unit Cost + (Direct Unit Cost x Indirect Cost %) + Overhead Rate.

  10. In the Unit Cost Calculation field, define whether the unit cost calculation should be based on the amount of time used or the number of units produced.

  11. Select the Specific Unit Cost field if you want to define the work center's unit cost on the routing line where it's being used. This setting might be relevant for operations with capacity costs that are different than what you would normally process at that work center.

  12. In the Flushing Method field, select whether manually or automatically calculate and post output at this work center using one of the following methods.

    Option Description
    Manual Manually post time used, output, and scrap in the output journal or production journal.
    Forward Automatically post output when you release the production order.
    Backward Automatically post output when you finish the production order.

    Note

    If necessary, the flushing method selected here can be overridden for individual operations by changing the setting on routing lines

  13. In the Unit of Measure Code field, enter the time unit in which this work center's cost calculation and capacity planning are made. To be able to constantly monitor consumption, you must first set up a method of measure. The units you enter are basic units. For example, the processing time is measured in hours and minutes.

    Note

    If you use Days, remember that one day is 24 hours, and not an eight hour work day.

  14. In the Capacity field, define whether the work center has more than one machine or person working at the same time. If your Business Central doesn't include the Machine Center functionality, then the value in this field must be 1.

  15. In the Efficiency field, enter the percentage of the expected standard output that this work center actually outputs. If you enter 100, it means that the work center has an actual output that is the same as the standard output.

  16. Turn on the Consolidated Calendar toggle if you're also using machine centers. This setting ensures that calendar entries are rolled up from machine center calendars.

  17. In the Shop Calendar Code field, select a shop calendar. For more information, see Create Shop Calendars.

  18. In the Queue Time field, specify a fixed time span that must pass before assigned work can begin at this work center.

Note

Use queue times to provide a buffer between the time that a component arrives at a machine or work center and when the operation actually starts. For example, a part is delivered to a machine center at 10:00 but it takes an hour to mount it on the machine so the operation does not start until 11.00. To account for that hour, the queue time would be one hour. The value of the Queue Time field on a machine or work center card plus the sum of the values in the Setup Time, Run Time, Wait Time, and Move Time fields on the item routing line combine to give the production lead time of the item. This helps provide accurate overall production times.

Considerations about capacity

The capacity and efficiency for work and machine centers affect more than just the available capacity. The values also affect the overall production time that consists of the setup time and run time, which are both defined on the routing line.

When you allocate a routing line to a work or machine center, Business Central calculates:

  • How much capacity is needed.
  • How long the operation takes to complete.

Run time

To calculate the run time, the system allocates the exact time that is defined in the Run Time field of the routing line. Efficiency and capacity don't affect the allocated time. For example, if the run time is defined as 2 hours, then the allocated time is 2 hours, regardless of values in the efficiency and capacity fields in the work center.

Note

The capacity that is used in the calculations is defined as the minimal value between the capacity that is defined in the work or machine center and the concurrent capacity that is defined for the routing line. If a work center has a capacity of 100, but the concurrent capacity for the routing line is 2, then 2 will be used in the calculations.

The duration of an operation, on the contrary, considers both efficiency and capacity. Duration is calculated as Run Time / Efficiency / Capacity. The following list shows a few examples of the calculation of duration for the same run time, which is defined as 2 hours for the routing line:

  • Efficiency 80% means you need 2.5 hours instead of two hours

  • Efficiency 200% means you can complete the work in one hour. You can dig the hole twice as fast if you have an excavator that is twice the size of the smaller one

    You can get the same result if you use two smaller excavators instead of a large one. Use 2 as the capacity and 100% as the efficiency

Fractional capacity is tricky. We'll discuss it later in this article.

Setup time

Time allocation for the setup time depends on the capacity and is calculated as Setup Time * Capacity. For example, if the capacity is set to 2, your allocated setup time doubles because you must set up two machines for the operation.

Duration of setup time depends on efficiency and is calculated as Setup Time / Efficiency.

  • Efficiency 80% means you need 2.5 hours instead of two hours to set up.
  • Efficiency 200% means you can complete setup in 1 hour instead of 2 hours defined in the routing line.

The fractal capacity is used only in specific cases.

Work center processing multiple orders simultaneously

Let's use a paint-spraying booth as an example. It has the same setup and run times for each processed lot. But each lot can contain multiple individual orders that are painted simultaneously.

In this case, the setup time and the concurrent capacity manage the cost allocated to orders. We recommend that you don't use run time in routing lines.

The allocated setup time for each individual order will be in reverse order of the number of orders (quantities) that are executed simultaneously. Here are some more examples of the calculation of setup time when that is defined as two hours for the routing line:

  • If there are two orders, then the concurrent capacity in the routing line should be set to 0.5.

    As a result, the allocated capacity for each is one hour, but the duration for each order remains two hours.

  • If there are two orders with a quantity of one and four, respectively, then the concurrent capacity for the routing line of the first order is 0.2, and 0.8 for the second.

    As a result, the allocated capacity for the first order is 24 min and 96 for the second one. The duration for both orders remains two hours.

In both cases, the total allocated time for all orders is two hours.

Efficient resource can dedicate only part of their work date to productive work

Note

This scenario is not recommended. We recommend that you use efficiency instead.

One of your work centers represents an experienced worker who works with 100% efficiency on tasks. But they can only spend 50% of their working time on tasks because the rest of the time they solve administrative tasks. While this worker is capable to complete a two hour task in exactly two hours, in average you must wait another two hours while the person is dealing with other assignments.

The allocated run time is two hours, and the duration is four hours.

Don't use setup time for such scenarios because Business Central only allocates 50% of the time. If the setup time is set to 2, the allocated setup time is one hour, and the duration is two hours.

Consolidated calendar

When Consolidated calendar field is selected, then the work center has no capacity of its own. Instead, its capacity is equal to the sum of the capacities of all the machine centers that are assigned to the work center.

Note

The efficiency of the machine center is converted to the capacity of the work center.

For example, if you have two machine centers with an efficiency of 80 and 70, respectively, the consolidated calendar entry has:

  • An efficiency of 100
  • A capacity of 1.5
  • A total capacity of 12 hours (eight hour shift * 1.5 capacity).

Note

Use the Consolidated Calendar field when you structure your routings to schedule production operations at the machine center level, not the work center level. When you consolidate the calendar, the Work Center Load page and reports become an overview of the aggregate load in all machine centers that are assigned to the work center.

Example - Different machine centers assigned to a work center

It's important to plan which capacities make up the total capacity when you set up machine centers and work centers.

If different machine centers (such as 210 Packing table 1, 310 Painting Cabin...) are assigned to a work center, the consideration of the single capacities of the machine centers is significant because the failure of one machine center can interrupt the entire process. The machine groups can be entered according to their capacity but they aren't included in planning. If you turn off the Consolidated Calendar toggle, only the capacity of the work center is assigned in the planning. The machine center capacity is excluded.

If, however, you combine identical machine centers (such as 210 Packing table 1 and 220 Packing table 2) in a work center, you can consider the work center as a sum of the assigned machine centers. Therefore, the work center is listed with zero capacity. If you turn on the Consolidated Calendar toggle, the common capacity is assigned to the work center.

If you don't want the capacities of work centers to contribute to the total capacity, specify 0 in the Efficiency field.

To set up a capacity constrained machine or work center

You must set up production resources that you regard as critical and mark them to accept a finite load instead of the default infinite load that other production resources accept. A capacity-constrained resource can be a work center or machine center that's a bottleneck and would like to establish a limited, finite load for.

Business Central doesn't support detailed shop floor control. It plans for a feasible utilization of resources by providing a rough-cut schedule, but doesn't automatically create and maintain detailed schedules based on priorities or optimization rules.

On the Capacity Constrained Resources page, you can create a setup to prevent resources from becoming overloaded. The setup can also ensure that capacity isn't left unallocated if it could increase the turn-around time of a production order. In the Dampener (% of Total Capacity) field, you can add dampener time to resources to minimize operation splitting. This setting enables the system to schedule load on the last possible day by slightly exceeding the critical load percent. Exceeding the load percent can reduce the number of operations that are split.

When you plan with capacity-constrained resources, Business Central ensures that resources aren't loaded above their capacity (critical load). It assigns each operation to the nearest available time slot. If the time slot isn't large enough to complete the entire operation, the operation is split into two or more parts in the nearest available time slots.

  1. Choose the Lightbulb that opens the Tell Me feature. icon, enter Capacity Constrained Resources, and then choose the related link.
  2. Choose the New action.
  3. Fill in the fields as necessary.

Note

Operations on work centers or machine centers that are set up as constrained resources are always planned serially. This planning means that if a constrained resource has multiple capacities, those capacities must be planned in sequence. You can't plan them in parallel like they would be if the work or machine center wasn't set up as a constrained resource. For a constrained resource, the Capacity field on the work center or machine center is greater than 1.

In case of operation splitting, the setup time is only assigned one time because it's assumed that some manual adjustment is done to optimize the schedule.

See also

Create Shop Calendars
Setting Up Manufacturing
Manufacturing
Planning
Inventory
Purchasing
Work with Business Central

Find free e-learning modules for Business Central here