Practice manager Power BI content

This article describes what is included in the Practice manager Microsoft Power BI content. It explains how to access the Power BI reports, and provides information about the data model and entities that are used to build the content.

Overview

The Practice manager Power BI content was created for practice managers and project managers. It provides key metrics that are related to the projects that the organization is working on. The dashboard gives an overview of the projects and related customers. A report-level filter can be used to report for specific legal entities. This Power BI content pulls data from the project accounting aggregate measurements.

The Practice manager Power BI content contains five report pages: one overview page, and four pages that provide details about project costs, revenues, earned value management, and hour metrics that are broken down across various dimensions.

All the amounts in the content are shown in the system currency. You can set the system currency on the System parameters page.

Accessing the Power BI content

The Practice manager Power BI content is shown in the Project management workspace.

Reports that are included in the Power BI content

The following table provides details about the metrics that are found on each report page in the Practice manager Power BI content.

Report page Metrics
Projects overview
  • Created projects
  • Estimated projects
  • In-process projects
  • Actual revenue by customer
  • Budget gross margin by project
  • Earned value management overview
Cost
  • Actual vs. budget cost by month
  • Actual vs. budget cost by year
  • Actual vs. budget cost by category
  • Actual cost by transaction type
Revenue
  • Actual revenue by month
  • Actual revenue by postal code
  • Actual vs. budget revenue by category
  • Actual revenue by customer industry
EVM Cost and schedule performance index by project
Hours
  • Actual billable utilized hours vs. actual billable burden hours vs. budget hours
  • Actual billable utilized hours vs. actual billable burden hours by project
  • Actual billable utilized hours vs. actual billable burden hours by resource
  • Actual billable hours ratio by project
  • Actual billable hours ratio by resource

The charts and tiles on all these reports can be filtered and pinned to the dashboard. For more information about how to filter and pin in Power BI, see Create and configure a dashboard. You can also use the Export underlying data functionality to export the underlying data that is summarized in a visualization.

Understanding the data model and entities

The following data is used to fill the report pages in the Practice manager Power BI content. This data is represented as aggregate measurements that are staged in the Entity store. The Entity store is a Microsoft SQL Server database that is optimized for analytics. For more information, see Power BI integration with Entity store.

The following sections describe the aggregate measurements that are used in each entity.

Entity: ProjectAccountingCube_ActualHourUtilization

Data source: ProjEmplTrans

Key aggregate measurement Field Description
Actual billable utilized hours Sum(ActualUtilizationBillableRate) The total of actual billable utilized hours.
Actual billable burden hours Sum(ActualBurdenBillableRate) The total of the actual burden rate.

Entity: ProjectAccountingCube_Actuals

Data source: ProjTransPosting

Key aggregate measurement Field Description
Actual revenue Sum(ActualRevenue) The total of posted revenue for all transactions.
Actual cost Sum(ActualCost) The total of posted cost for all transaction types.

Entity: ProjectAccountingCube_Customer

Data source: CustTable

Key aggregate measurement Field Description
Number of projects COUNTA(ProjectAccountingCube_Projects[PROJECTS]) The count of available projects.

Entity: ProjectAccountingCube_Forecasts

Data source: ProjTransBudget

Key aggregate measurement Field Description
Budget cost Sum(BudgetCost) The total of forecast cost for all transaction types.
Budget revenue Sum(BudgetRevenue) The total of forecast accrued/invoiced revenue.
Budget gross margin Sum(BudgetGrossMargin) The difference between the sum of total forecast revenue and the sum of total forecast cost.

Entity: ProjectAccountingCube_ProjectPlanCostsView

Data source: Project

Key aggregate measurement Field Description
Planned cost Sum(SumOfTotalCostPrice) The total cost price in estimates for all project transaction types that have planned tasks.

Entity: ProjectAccountingCube_Projects

Data source: Project

Key aggregate measurement Field Description
Cost performance index ProjectAccountingCube_Projects[Earned value] ÷ ProjectAccountingCube_Projects[Total actual cost of completed tasks] The calculation of the total earned value divided by the total actual cost.
Schedule performance index ProjectAccountingCube_Projects[Earned value] ÷ ProjectAccountingCube_Projects[Total planned cost of completed tasks] The calculation of the total earned value divided by the total planned cost.
Percentage of work completed Percentage of work completed = ProjectAccountingCube_Projects[Total actual cost of completed tasks] ÷ (ProjectAccountingCube_Projects[Total actual cost of completed tasks] + ProjectAccountingCube_Projects[Total planned cost of project] – ProjectAccountingCube_Projects[Total planned cost of completed tasks]) The total percentage of completed work, based on the total actual cost of completed tasks and the planned cost of the project.
Actual billable hours ratio ProjectAccountingCube_Projects[Project total actual billable utilized hours] ÷ (ProjectAccountingCube_Projects[Project total actual billable utilized hours] + ProjectAccountingCube_Projects[Project total actual billable burden hours]) The total actual billable hours, based on the utilized hours and the burden hours.
Earned value ProjectAccountingCube_Projects[Total planned cost of project] × ProjectAccountingCube_Projects[Percentage of work completed] The total planned cost multiplied by the percentage of completed work.

Entity: ProjectAccountingCube_TotalEstimatedCosts

Data source: ProjTable

Key aggregate measurement Field Description
Completed activity planned cost Sum(TotalCostPrice) The total cost price in estimates for all project transaction types that have completed tasks.