Contains constants that specify the type of task to insert on the Timeline view in Project.
| Name | Value | Description |
|---|---|---|
| pjTimelineInsertCalloutTask | 2 | Insert a callout task, where the task information is shown in a callout box attached to the timeline. |
| pjTimelineInsertMilestone | 1 | Insert a milestone (a task with 0 days duration). |
| pjTimelineInsertTask | 0 | Insert a task. |