True if the remaining work on a task that is scheduled after the status date is moved to start at the status date. Read/write Boolean.
Syntax
expression. AndMoveRemaining
expression A variable that represents a Project object.
Remarks
The AndMoveCompleted and AndMoveRemaining properties can also be set with the OptionsCalculation method.