Follow these steps to finish a production order.

  1. Click Production control > Periodic > Production orders > End.

  2. In the All production orders list page, select a production order line. Click the Production order tab. On the Action Pane, click End.

  3. If the production job is not reported as finished, select the Report as finished check box on the General tab.

  4. Select the scrap method, and then click OK.

The production order is assigned the Ended status and can no longer be updated. The production order is cost accounted, and a receipt transaction with the Purchased status is generated for the produced item. All journals associated with the production order are closed.