Worker hour rate report (ProjListProjHourRateEmplItem)

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Use this report to analyze rate per hour, value-added rate per hour, cost per hour, and gross margin per hour by project.

How to filter the data on this report

When you generate this report, the following default parameters are displayed. You can use these parameters to filter the data that will be displayed on the report. For more information, see Filter the data on a report.

Field

Description

Include project types

Select the project types that you want to include on the report. You must select at least one project type.

Include transaction types

Select the transaction types that you want to include on the report. By default, hour transaction types are included on the report.

(Project date)

From date / To date

Specify a starting date and an ending date for hour transactions posted to projects to include on the report.

(Ledger date)

From date / To date

Specify a starting date and an ending date for hour transactions posted to the general ledger to include on the report.

Actual vs. budget

Select Actual to display actual values on the report.

Select Budget to display budgeted values on the report.

Forecast model

Select the forecast model that you want the report to use.

Note

If you are using project budget control, select the budget forecast model that is used by this project.

Skip blank ID

Select whether to exclude transactions that are not assigned to a project.

Skip zero

Select whether to exclude all rows on the report where the amounts are equal to zero.

Item number

Click Select. In the Worker hour rate form, in the Criteria field, select an item number to include on the report. To add more than one item, click Add.

Service subscription

Click Select. In the Worker hour rate form, in the Criteria field, select a service subscription to include on the report. To add more than one service subscription, click Add.

How to work with reports

The following topics explain how to print a report and how to filter and sort the data on a report.

Details of this report

The following table explains where to find the report in the Application Object Tree (AOT) and how to navigate to the report in the Microsoft Dynamics AX client.

Detail

Description

Name of report in the AOT

ProjHourRateEmpl

Location of report in the AOT

SSRS Reports\Reports\ProjHourRateEmpl

Menu item of the report

ProjListProjHourRateEmplItem

Navigation to the report

Click Project management and accounting > Reports > Project statements > Hour rate > Worker hour rate.

Where the data in this report comes from

The data on this report comes from the following sources:

  • ProjListProjHourRateEmplItemDP.processReport

  • DirPerson table

  • HcmWorker table

  • InventTable table

  • ProjListProjProfitLossTmp table

  • SMASubscriptionTable

Note

To determine where the data in the temp tables comes from, view the cross-references for the ProjListProjHourRateEmplItemDP.processReport class.

If you are a developer, you can learn more about where the data on a report comes from by using the following procedure.

  1. Open the AOT.

  2. Locate the report in the SSRS Reports\Reports node.

  3. Right-click the report and click Add-Ins > Cross-reference > Using (instant view).