PredecessorLink Element
This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.
Defines the predecessor task on which this task depends for its start or finish date.
<PredecessorLink>
ComplexTypeValue
</PredecessorLink>
Parent Elements
Child Elements
Element |
Required/Optional |
Description |
---|---|---|
Optional |
Unique ID number for the predecessor task. |
|
Optional |
Type of predecessor task link (FF, FS, SF, SS). |
|
Optional |
Indicates whether the task predecessor is part of another project. |
|
Optional |
External predecessor project. |
|
Optional |
Amount of lag time (in tenths of a minute) from the predecessor task. |
|
Optional |
Indicates the time format (hours, days, and so on) for the amount of lag specified in LinkLag. |
Occurrences
Minimum: 0 Maximum: Unbounded |