APPLIES TO:
Azure Data Factory
Azure Synapse Analytics
Tip
Try out Data Factory in Microsoft Fabric, an all-in-one analytics solution for enterprises. Microsoft Fabric covers everything from data movement to data science, real-time analytics, business intelligence, and reporting. Learn how to start a new trial for free!
This article helps you understand nested activities in Azure Data Factory and Azure Synapse Analytics and how to use them, limitations, and best practices.
A Data Factory or Synapse Workspace pipeline can contain control flow activities that allow for other activities to be contained inside of them. Think of these nested activities as containers that hold one or more other activities that can execute depending on the top level control flow activity.
See the following example with an If activity that has one activity contained.
The following control flow activities support nested activities:
Control activity | Description |
---|---|
For Each | ForEach Activity defines a repeating control flow in your pipeline. This activity is used to iterate over a collection and executes specified activities in a loop. The loop implementation of this activity is similar to the Foreach looping structure in programming languages. |
If Condition Activity | The If Condition can be used to branch based on condition that evaluates to true or false. The If Condition activity provides the same functionality that an if statement provides in programming languages. It evaluates a set of activities when the condition evaluates to true and another set of activities when the condition evaluates to false. |
Until Activity | Implements Do-Until loop that is similar to Do-Until looping structure in programming languages. It executes a set of activities in a loop until the condition associated with the activity evaluates to true. You can specify a timeout value for the until activity. |
Switch Activity | The Switch activity provides the same functionality that a switch statement provides in programming languages. It evaluates a set of activities corresponding to a case that matches the condition evaluation. |
There are two primary ways to navigate to the contained activities in a nested activity.
Each control flow activity that supports nested activities has an activity tab. Selecting the activity tab will then give you a pencil icon you can select to drill down into the inner activities panel.
From the activity on the pipeline canvas, you can select the pencil icon to drill down into the inner activities panel. Additionally, the ForEach and Until activities support double-clicking on the activity to drill down to the inner activities panel.
Your pipeline canvas will then switch to the context of the inner activity container that you selected. There will also be a breadcrumb trail at the top you can select to navigate back to the parent pipeline.
There are constraints on the activities that support nesting (ForEach, Until, Switch, and If Condition), for nesting another nested activity. Specifically:
See the best practices section below on how to use other pipeline activities to enable this scenario. In addition, the Validation Activity can't be placed inside of a nested activity.
If and Switch can be used inside ForEach or Until activities. ForEach or Until supports only single level nesting If and Switch can't be used inside If and Switch activities.
In order to have logic that supports nesting more than one level deep, you can use the Execute Pipeline Activity inside of your nested activity to call another pipeline that then can have another level of nested activities. A common use case for this pattern is with the ForEach loop where you need to additionally loop based off logic in the inner activities.
An example of this pattern would be if you had a file system that had a list of folders and each folder there are multiple files you want to process. You would accomplish this pattern, generally, by performing the following.
The parent pipeline would look similar to the below example.
The child pipeline would look similar to the below example.
See the following tutorials for step-by-step instructions for creating pipelines and datasets.
Events
Mar 31, 11 PM - Apr 2, 11 PM
The biggest Fabric, Power BI, and SQL learning event. March 31 – April 2. Use code FABINSIDER to save $400.
Register todayTraining
Module
Orchestrating data movement and transformation in Azure Data Factory - Training
Orchestrate data movement and transformation in Azure Data Factory or Azure Synapse Pipeline
Certification
Microsoft Certified: Fabric Data Engineer Associate - Certifications
As a Fabric Data Engineer, you should have subject matter expertise with data loading patterns, data architectures, and orchestration processes.