High-risk scenarios

Completed

There are several scenarios, which could introduce more risk to the data migration workstream if they aren't managed appropriately. A risk is also if the project timeline doesn't allow for sufficient discovery, design, development, and testing. These scenarios include:

  • When the customer takes ownership for the entire data migration workstream without appropriate engagement from the partner
  • Product renumbering (change management for users, master data changes, and opening balance changes to adhere to a new scheme)
  • New chart of accounts
  • Overly complex data migration team structure
  • Not planning for dress rehearsals/mock cutovers